Fire Sprinkler Water Supply Remediation
- Commercial Class 7b
- Project was a 24-hour live site
- Fire Water Supply Failure in Street (incoming supply)
- Emergency call out works
- Foot Path closure & diversion of pedestrian traffic
- Produce traffic guidance scheme & risk assessment for public domain works
- Non-destructive digging
- Council applications, permits & bonds
- Authority coordination
- High pressure fuel pipeline (VIVA)
- High voltage electrical cables (AUSGRID)
- High pressure gas pipeline (JEMENA)
- Coordinate shutdown & isolation of the base building sprinkler system
- Coordinate shutdown of fire system with NSWFR
- 2m deep service trench
- Expose pipe failure
- Rectify failure
- Reinstate footpath
- Pressure test service
- Oversee recommission of the fire system
- 12 months DLP